As water becomes more and more precious, the refuge is striving to make the best use of every drop with a multi-year project of replacing aging and failing water infrastructure. Improved water infrastructure will ensure the most efficient use of the refuge’s limited water, assisting with the growth of native seeds and tubers for migrating birds and providing wetland habitat for listed species, birds and wildlife. A healthy refuge also provides a major economic contribution to the local and state economy and provides opportunities for birders, photographers, children, families and nature lovers to enjoy a wild and beautiful place.
In the spring of 2026, months of research and planning began to take shape. Refuge staff carefully determined a list of priority water infrastructure that needed to be repaired. Friends launched the Water for the Wild campaign, and thanks to your generous support, also earned two matching grants. Refuge staff then began the quiet work of getting permits and approvals over the summer months.
The initial plan was to replace five key water infrastructures, but when the contractor visited the site to plan the work, he noted that he could pull from materials already on-site and do more than the original five gates. The project expanded into ten infrastructures, including the beloved boardwalk inflow gate, and the dredging of a vital drainage ditch that services five of the wetlands, benefiting roughly 645 acres across thirteen wetland units.
Work began Oct 2, 2026 and continued through mid-November. More infrastructure projects are needed and will be planned as funding comes available. The following “Work Journal” documents the construction process in words and pictures.
Water for the Wild Construction Phase 1 Work Journal – Oct/Nov 2026
Work moved along beautifully to replace and improve ten water infrastructures and dredge a major ditch at Bosque del Apache. Mike Lopez of Lopez Precision LLC and his crew often worked from sunrise to sunset seven days a week to get this project done quickly. Construction began with the most visible work right at the refuge entrance, and then moved through a series of gates, culverts, inflow and outflow structures along a seasonal road and Bosque Road before becoming more visible again at the Boardwalk area.
Pictures really tell the story of how dilapidated the structures were and illustrate that they had reached the end of their usefulness. New gates and culverts, and improved structural reinforcement will now allow water to get where it is needed more efficiently and quickly.
2-WAY SCREWGATE, CULVERT AND DITCH
One of the biggest projects completed was at the entrance to the refuge and included replacing a large culvert running under the Flight Deck road, the screwgate providing water to the Flight Deck wetland and more, and dredging the first section of the major ditch running from this gate up to the Eagle Scout deck.
As you enter the refuge, your first view is of two of the largest wetland units on the refuge. You may not realize that every time you turn left, you are driving over a key culvert that guides water into these fields, and you are passing a significant ditch that serves five of our wetland areas. On your next visit, you will see a beautifully dredged ditch that can now move water unimpeded, and you’ll notice a large, newly constructed headgate that will control water flow to make the best use of every available drop. What you won’t see is the substantial new culvert buried deep under the road that directs water through the gate and into those wetlands that winter birds – and visitors – love.

The crew replaced a headgate that directs water into some of the largest feeding and resting wetland areas on the refuge, as well as a major culvert running under the North Loop tour road.
Dredging the 2-way ditch from this new gate to the Eagle Scout deck included removing accumulated sediment, reusing the excavated material to reshape and narrow the ditch and restoring the adjacent service road. This work created a more defined channel, improving the efficiency and effectiveness of water conveyance and drainage to and from the associated wetlands units.
This critical infrastructure supports water management across five wetland units totaling 420 acres, with a combined maximum seed yield potential of more than 1.6 million pounds. These units comprise some of the refuge’s largest and most publicly viewed wetland units, including two with observation decks providing opportunities for wildlife viewing, birding, photography and environmental education. During winter months, these units provide roosting, loafing and feeding habitat for thousands of sandhill cranes and snow geese, as well as diverse assemblages of diving and dabbling ducks and other wildlife. During the summer months, listed species, including the Southwestern Willow Flycatcher and New Mexico Meadow Jumping Mouse, rely on some of the wetland habitats supported by this infrastructure. Construction included replacing the 36-inch diameter culvert that runs under the Flight Deck road, installing a new screwgate and improving the screwgate structure with the installation of concrete wingwalls.
2-way screwgate before and after:

2-way ditch before and after:

WETLANDS AND GATES ALONG THE NORTH TOUR LOOP SEASONAL ROAD
The crew next moved on to a series of infrastructures along the seasonal road that begins at the Eagle Scout deck on Bosque Road and ends at the North Loop, including five culverts, gates or outflow structures. Again, these are likely not something you ever noticed. Culverts under the road quietly direct water through inflow and outflow structures into the wetlands. As with many of the culverts and gates, they were worn, collapsing, and one gate was so eroded that half of it was missing! These structures were working well below capacity, but are now being replaced and will be functioning beautifully, thanks to your generous support.

MOHAWK DITCH
The Mohawk Ditch outflow, which consists of a screwgate and culvert, supports water management across three wetland units totaling 238 acres, with a combined maximum seed yield potential of more than 1.1 million pounds. These units comprise more of the refuge’s largest and most publicly viewed wetland units, including one with an observation deck providing opportunities for wildlife viewing, birding, photography and environmental education. Thousands of sandhill cranes and snow geese, as well as an array of diving and dabbling ducks and other wildlife enjoy these wetlands.
The existing culvert was rotted and the inflow gate was broken in half! Construction included the complete replacement of a 36-inch diameter culvert and installation of a beautiful new screwgate. You can imagine how well this new system can now manage water!
Old and new screwgates:

Rusted-through old culverts and brand new culverts being installed:

Further along this same road, a series of four more badly corroded and failing water infrastructures were also replaced:

WETLAND UNIT 24A-NORTH
The crew then moved further down Bosque Road to a structure supporting the last large wetland on your right as you drive from the refuge entrance. This wetland is a productive 25.9 acre moist-soil unit with a maximum seed yield potential of 168,466 pounds. It provides important wildlife viewing opportunities for visitors while supporting critical waterfowl and listed species habitat. The structures feeding water to this unit were collapsing and corroded. The crew completely replaced the 24-inch diameter culvert and screw gate and installed concrete wingwalls. This structure gives renewed life to a key wetland for birds, wildlife, and visitors to enjoy.
Before and after – Old gate collapsing into the waterway; what you can’t see is the badly corroded and silted culvert beneath your feet:

New gate and culvert, post instillation:

Photo by Stede Barber
The crew finally moved over to the Boardwalk area along the South Loop, where work for this season wrapped up. The structures that the crew worked on in this area support wetlands that are some of the best producers of food for migratory birds, listed species and wildlife on the refuge. They also have some of the best access to existing water and are favored not only by birds and wildlife, but are also visible to guests who come to photograph and enjoy the wonder and beauty of Bosque del Apache.
Work is now complete for this season, and water is already returning to the wetlands that birds, wildlife and visitors love!

Photo by Douglas Maahs
Did you know that in addition to grants, an incredible 51% of the funds for this project so far were provided by your generous donations?! That is impressive! We couldn’t do this without you, and we thank you again and again for your massive support, which made these first steps of an essential project possible!
This is the beginning of a larger project to protect the refuge by improving the water infrastructure system. A complete survey of all water infrastructure at the refuge has been completed, the next set of structures in need of improvement/replacing has been prioritized, and Lopez Precision LLC is measuring and creating a plan for how best to proceed from here. We are once again applying for grants and we still welcome your continued support, which will help keep this project alive.
If you’d like to help continue improving water infrastructure at Bosque del Apache, please go to https://secure.friendsofbosquedelapache.org/a/waterforthewild. We gratefully welcome your ongoing support!